1.Building design, control
2.House commercial facilities, apartment complex, Japanese-style building
3.First class authorized architect office
■Governor of Gifu registration 8351

 

Faq

From a question put to our office, I place particularly many inquiries and the answer.
Or an inquiry form calls if you have any questions as well as the following contents (058-274-1448)
Ask it by FAX (058-274-1446) casually.

Q&A (common question and answer)

※When the answer to following questions clicks "+" button, I am displayed

Q1. How much are the design charges?

A1:

The design control charges are decided based on former Ministry of Construction notification 1206.
Our drawing office calculates design control charges in consideration of a kind, a degree of difficulty, the area of the building to a base in this
1206, too.
The following tables are approximate indications, but please refer to it.

 Construction construction cost  Design control charges
 In the case of a construction construction cost to 20 million yen  2 million yen
 In the case of the construction construction cost to 20 million yen - 30 million yen  10% of construction construction costs
 In the case of the construction construction cost to 30 million yen - 50 million yen  9% of construction construction costs
 In the case of the construction construction cost to 50 million yen - 80 million yen  8% of construction construction costs
 In the case of a construction construction cost to 80 million yen - 10,000 ten thousand Japanese yen  7% of construction construction costs
In the case of a construction construction cost to 10,000 ten thousand Japanese yen - 30,000 ten thousand Japanese yen  6% - 7% of the construction construction cost


●Of a building "examines the structural calculation compatibility judgment" in the case of building certification application may become a target.
 In that case, I add it to each design control charges mentioned above by 0.5% each.
  In the case of a construction construction cost to example 1) 20 million yen: Flat 2,100,000 yen
In the case of the construction construction cost to  example 2) 20 million yen - 30 million yen
: 9.5% of construction construction costs

●The following is not included in the amount of money of the table mentioned above.
 1 consumption tax
 2 building certification fees
 3 special permission application duties expense (takuzokyokasarusei, development permission application)
 4 ground investigation expenses
 Surveying expense (at a limit as for the surveying to be carried out by a drawing office a winged ant to be performed by 5 surveying experts
 Not precocious)


●In addition, I match the payment of design control charges with a progress degree of design control duties like the following tables and divide it and ask.

Payment time Payment amount of money
 At the time of contract establishment  10% of design control charges total sum
 After the enforcement design completion at the time of the construction contract contract conclusion  60% of design control charges total sum
 At the time of laying the roof  15% of design control charges total sum
 At the time of completion delivery  15% of design control charges total sum